The City received an update today from NCDOT regarding the projected schedule to open E. Boiling Spring Road and Pine Lake.

According to the Resident Engineer for NCDOT, the state‚Äôs contractor, Barnhill Construction, continues to backfill the site after NCDOT completed installation of the new drainage pipe system this past Friday, January 4th.  The pipe system itself sits on a bed of #57 stone and will be encapsulated by 4 feet of stone on top.  Barnhill anticipates to complete the stone work on January 9-10 and then begin filling the break with fill dirt.  Initial back fill may be completed by Monday, January 14th and the fine grading of the road and shoulder slope by the end of the week.  Depending on weather, the area may be paved by January 17-18.  